InDepth recently carried out a reservoir clean and sterilisation of a tower reservoir in Co. Wicklow. This tower had its difficulties as we had to plan a dechlorination of over 30,000 litres of water prior to cleaning.
Our client requested that the dechlorination, cleaning, sterilisation and re-energise of the reservoir all had to be completed within a 16-hour timeframe. This took a lot of planning and with the help of our partners in McBreen Environmental, we were able to complete this project all within a 10-hour time frame.
This was the 3rd reservoir on this particular site that was dechlorinated, cleaned and sterilised in a 14-day period and serves over 90,000 homes across Wicklow.
Well done to the InDepth and McBreen Environmental teams for their fantastic work on this project.